Sodium hydroxide solution tank construction in Hungary – precision in tank erection 

Sodium hydroxide solution tank construction in Hungary – precision in tank erection 

As part of a new industrial tank installation project, we introduced and implemented an advanced installation method for OLP-TECH Manufacturing, Assembly and Service Ltd. focusing on enhancing efficiency and optimizing the construction process. Our client previously utilized the “top-to-bottom” tank erection method but was looking for a more efficient and optimized tank assembly process.

Nordweld proposed an innovative electromechanical tank jacking system, which enables fast and precise assembly of steel storage tanks, significantly reducing construction time and minimizing the number of workers required on-site. The key factors behind choosing this solution were the need to lower transportation costs and optimize on-site work by introducing vertical plate Bending Machine and Plate Track. 

Technical specifications of the sodium hydroxide solution tank

  • Location: Kazincbarcika, Hungary
  • Tank Type: Stainless steel storage tank for sodium hydroxide solution
  • Diameter: 16 m
  • Height: 17 m
  • Weight: 120 t
  • Capacity: 3,000 m³
  • Material: Stainless steel 1.4404

Implementation of the advanced tank lifting system

To meet the high standards set by our client, we applied a modern tank lifting system, which included:

  • 16 x 15-ton electromechanical jacks for tank lifting 
  • 16 x wheel trolleys entire tank rolls on the top of wheels”   
  • 1 x weld gap adjusting jack, adjust the weld gap during sheet feeding from the bending machine
  • 5 x tank rotators, guaranteeing precise tank rotation adjusted to the speed of the welding process,
  • Tack Weld Stand, the horizontal joints are aligned as the tank rotates continuously,
  • Internal Scaffolding  system, create working platforms inside the tank ,
  • Vertical  Plate Bending Machine, allowing for on-site straight plates rolling,
  • 15-meter plate track, used in conjunction with a vertical Bending Machine, placed flat material onto the plate track and welds the vertical seams. .

The tank erection of electromechanical  jacks ensured stability and precision during assembly, eliminating structural misalignment and improving ergonomic conditions within the confined space of the chemical plant.

Challenges in tank erection and their solutions

  1. Tank structure leveling
    At the start of the erection process, deviations due to uneven ground were identified. We conducted detailed adjustments and re-leveling the wheel trolley according to the position of the bending machine, ensuring the tank structure was positioned precisely correspondingly  to the project specifications.
  2. Limited space on-site
    The tank was assembled within a large chemical complex, where space constraints were a major challenge. To address this, we utilized a plate track system, which enabled direct feeding of 13-meter steel sheets into the bending machine, significantly reducing material preparation time and logistics costs.
  3. Advanced welding technology
    Due to the strict welding requirements for stainless steel, we recommended to use TipTig welding technology provided by TipTig Company, which improved weld quality, increased efficiency, and minimized thermal distortion.

Tank construction progress – next steps in tank erection

The assembly of the upper sections, roof, and access system has been completed. In the coming weeks, the remaining tank components will be installed. Tank jacking equipment will continue to play a crucial role in ensuring safety and precision throughout the final stages of construction.

With Nordweld’s technology, you can shorten project execution time, reduce the number of workers required, and optimize tank assembly logistics.
Contact us today to learn more about our innovative tank jacking solutions.

Check out the latest images showcasing the progress of the tank erection process! Precision tank assembly is our specialty!

Tags

Read our other news

Nordweld

Nordweld tank building systems – Innovative tank construction solutions

Nordweld provides innovative and fully mechanized tank erection systems to optimize construction efficiency, reduce costs, and enhance worksite safety. Our tank jacking systems utilize top-down construction technology, ensuring all work is performed at ground level, minimizing the need for scaffolding and cranes.
Read more
Nordweld

Innovations in tank construction – Nordweld at StocExpo 2025

Another successful edition of StocExpo 2025 is behind us! Over two days, we engaged in inspiring discussions, showcased our advanced solutions, and connected with industry leaders shaping the future of tank construction.
Read more
Nordweld

Visit us at StocExpo 2025

In March StocExpo 2025 will open its doors, bringing together global leaders in tank storage, terminal operations, and industrial construction.
Read more

Contact us for further details about our technology