Uruguay 2020 – 2021
![Uruguay 2020 – 2021](https://nordweld.eu/app/uploads/2024/11/Uruguay_2021.jpg)
Nordweld’s tank building system was used from October 2020 until July 2021 to construct 11 tanks as part of a large-scale project in the port of Montevideo.
Project details:
Number of tanks | Diameter | Height | Weight | Capacity | Material |
---|---|---|---|---|---|
3 | 19 m | 20 m | 94,2 t | 5700 m³ | LDX 2101 |
2 | 19 m | 20 m | 107 t | 5500 m³ | carbon steel |
1 | 16,9 m | 20 m | 92 t | 4500 m³ | carbon steel |
3 | 13,7 m | 20,3 m | 77 t | 2900 m³ | carbon steel |
2 | 9 m | 14,5 m | 21,8 m | 920 m³ | stainless steel |
- Used tank building system: Advanced System with wheel trolley, bending machine and plate track, Arc Tig welding process of circumference for the stainless-steel tanks and SAW for the carbon steel tanks.