Skip to content

Sweden 2025

Sweden 2025

Nordweld delivered the Advanced System with Wheel Trolley for the construction of 2 industrial tanks in stainless steel LDX 2101 in Sweden. The project required a well-organized erection process combining the top-down method, tank rotation, and material processing from both coil and flat sheets. 

Technical parameters of the tanks 

Project: 2 stainless steel tanks 
Capacity: 10,300 m³ each 
Diameter: 25.6 m 
Height: 20 m 
Weight: 220 t per tank 
Material: stainless steel LDX 2101 
Shell thickness: 6–10 mm from coil 
Shell thickness: 11–15.5 mm from flat sheets 
Total production hours: 9,600 hours for 2 tanks 
Productivity rate: 22 man-hours per tonne 

The project scope included the construction of 2 tanks with a diameter of 25.6 m and a height of 20 m. Both tanks were made of stainless steel LDX 2101. Depending on the required shell thickness, the material was processed from both coil and flat sheets. 

Combining coil and flat sheet processing in one erection process 

One of the key aspects of the project was the combination of two material preparation methods within one tank construction process. For shell sections with a thickness of 6–10 mm, the material was processed directly from coil using the Vertical Bending Machine and Decoiler. For thicker shell sections, from 11 to 15.5 mm, Plate Track and a station for the vertical assembly and welding of sheet metal plates were used. 

This solution made it possible to adapt the material preparation method to the technical requirements of the tank shell while maintaining continuity in the assembly and welding of successive shell sections. 

Top-down construction, tank rotation and mechanized welding 

The project used a configuration including Lift Jacks 100-00 15T, Wheel Trolleys, Tank RotatorsVertical Bending Machine, DecoilerPlate Track, and automated Arc Tig welding stations for horizontal joints. The tank construction process was carried out using the top-down method, while tank rotation made it possible to perform key assembly and welding operations at ground level. 

As a result, it was possible to maintain an organized workflow, achieve better control over the welding process, and efficiently carry out successive erection stages, including roof assembly using the rotation system for the shoring tower. 

This project confirms that the Nordweld system effectively supports the construction of large stainless steel tanks where process control, repeatability, and flexible adaptation of the erection method to the tank parameters are essential. 

Looking for a proven system for stainless steel tank construction? 

Contact the Nordweld team. We will help you select the right system configuration for the tank parameters, material, and the required erection and welding process on site. 

See our other projects

Nordweld

Italy 2026 

  • Number of tanks: 2
  • Diameter: 24 m ft
  • Height: 17 m ft
  • Shell and bottom plates: carbon steel 273  lbs.
  • Used tank building system: Standard System 
Read more
Nordweld

Italy 2026

  • Number of tanks: 3
  • Diameter: 36 m ft
  • Height: 7 m ft
  • Shell and bottom plates: carbon steel 273  lbs.
  • Used tank building system: Standard System with roller beds, tank rotators and lift jacks. 
Read more
Nordweld

Hungary 2025

  • Number of tanks: 1
  • Diameter: 16 m / 52,49 ft ft
  • Height: 17 m / 55,77 ft
  • Weight: 120 t / 264555 lbs.
  • Capacity: 3000 m³ / 792516 gal.
Read more

Allow us to introduce our tank building system to you

Now available! Get for free our brand-new e-book and learn how to reduce tank building costs up to 50%.

Download the free e-book