Hungary 2025

Hungary 2025

In January 2025, we completed our first project in Kazincbarcika, Hungary. We provided key equipment for the construction of a sodium hydroxide solution tank at one of the chemical complexes in the region.

Project details:

  • Number of tanks: 1
  • Diameter: 16 m
  • Height: 17 m
  • Weight: 120 t
  • Capacity: 3000 m3
  • Material: 1.4404 Stainless Steel

Technologies and equipment used
For the construction of the sodium hydroxide tank, we used:

  • 16 x 15 t lift jacks
  • 16 x wheel trolleys
  • 5 x tank rotators
  • 1 x tack weld stand
  • bending machine
  • 15 m plate track where a flat sheet was vertically welded and then passed through a bending machine

Efficient solution for limited space and cost savings
One of the key challenges was the limited space available around the tank during construction. To address this, we implemented a plate track solution that allowed 13-meter-long sheets to be directly fed into the bending machine and bent to the required angle.

Nordweld – proven solutions for tank construction projects for sodium hydroxide
This project is further proof that our solutions are effective even in the most demanding conditions. Thanks to our experience and the use of advanced technologies, we deliver the highest quality stainless steel tank construction worldwide.

Contact us and see how we can provide innovative tank solutions for your project.

See our other projects

Nordweld

Austria 2024

We have completed another project in which we constructed a high-quality stainless steel tank for a pulp and paper factory in the Wolfsberg area.
Read more
Nordweld

France 2024

We are excited to announce the completion of two tanks built with the advanced system for the wine industry in the picturesque Bordeaux region. These modern tanks feature a diameter of 16.47 m and a height of 16.8 m, with an impressive capacity of 3,400 m³. They are made of LDX 2101 material, which ensures exceptional quality and durability.
Read more
Nordweld

Finland 2024

In January 2024, TLC and Nordweld joined forces to collaboratively undertake the construction of a phosphoric acid tank in Finland, emphasizing the comprehensiveness of the project.
Read more

Allow us to introduce our tank building system for you